| CASE
STUDY #1 (WESTERN AUSTRALIA)
A refueling facility in Perth was to be decommissioned,
however, the environmental site assessment identified
approximately 25,000 m3 of TPH-impacted soil, with
concentrations ranging from 500 to 25,000 mg/kg TPH,
extending under most of the site. Estimated cost of
remediation was well in excess of $250,000.
The environmental consultant approached
the WA regulators and negotiated the use of the TPHCWG
methodology to conduct a risk-based assessment of
the TPH impact. The HRA was based on 14 HRAF analyses
of samples taken over a grid pattern and at various
depths within the TPH-impacted zone. Of these 14 samples,
5 indicated results in excess of criteria. These results
were plotted as a HRAF histogram and used to produce
a HRA based on various exposure pathways (e.g. soil
ingestion, inhalation of vapours emitted by semi-volatile
TPH fractions).
The HRA was approved by the WA regulators
and the need for costly soil remediation/removal was
avoided. A risk-based site management plan (SMP) is
currently ongoing, in order to ensure that the soil
TPH impact is not adversely impacting the underlying
groundwater aquifer. The cost of this SMP to date
is around $60,000, with small incremental costs expected
in the medium term for groundwater monitoring before
site closure is achieved. Significant cost savings
were achieved by application of the TPHCWG method
in this case.
CASE STUDY #2 (TASMANIA)
During validation of an old fuel depot located in
Tasmania, extensive TPH impact ranging in concentration
from 3,000 to 12,000 mg/kg TPH was identified around
the former drum platform and lube oil storage. No
BTEX or PAH constituents were identified, however,
site closure could not be achieved due to exceedance
of the regulatory TPH criteria (1000 mg/kg). The site
is characterised by clay soils, low temperatures and
high rainfall, all of which are not conducive to soil
bioremediation efforts. Eventually the site was completely
covered in impacted stockpiles up to 3 metres in height,
remediating slowly. The regulators required that further
site assessment be conducted around the impacted area,
however, this proved impossible due to space constraints.
The environmental consultant approached
the Tasmanian regulators and negotiated the use of
the TPHCWG methodology to conduct a preliminary risk-based
assessment on part of the TPH impacted stockpile.
The primary purpose of the HRA was to negotiate backfilling
of the sampled stockpile in order to allow the further
site assessment activities required by the regulators.
Five samples were taken from the
stockpile selected to be backfilled and analysed by
HRAF. Based on the HRAF data, a HRA was conducted
based on various exposure scenarios for the backfilled
soils. The results indicated that with minor soil
management, exposure and human health risk would be
negligible. The HRA was presented to the regulators,
who subsequently approved the backfilling of 700 m3
of soil still containing up to 6000 mg/kg TPH. The
remainder of the stockpiles are being sampled and
analysed in a similar manner. HRAF analysis, combined
with a sound and technically defensible risk assessment
approach, is currently saving the client considerable
time and expense in achieving site closure.
|